A small medical waste incinerator is quick to install β if the site is ready when it arrives. This checklist covers everything to prepare for the MWI-20, MWI-30 or MWI-50.
Footprint and Weight
| MWI-20 | MWI-30 | MWI-50 | |
|---|---|---|---|
| Dimensions (mm) | 1600 Γ 1200 Γ 1700 | 1700 Γ 1250 Γ 2500 | 1800 Γ 1300 Γ 3000 |
| Weight | ~1,600 kg | ~2,500 kg | ~4,600 kg |
| Chimney | 6 m, Γ280 | 6 m, Γ280 | 10 m, Γ330 |
| Power | 220V, 50/60 Hz | 220V, 50/60 Hz | 220V/50Hz or 380V/50Hz |
Site Checklist
- Concrete foundation β level, reinforced, larger than the unit footprint with working space around it; designed for the unit weight.
- Roof or shelter β protects the burners and control box from rain; allow the chimney to pass through or beside it.
- Clear space around the unit for loading, ash removal and maintenance.
- Power supply β correct voltage and frequency with a lockable isolator; generator backup where the grid is unreliable.
- Fuel tank β placed at a safe distance from the burner, with a bund to catch leaks.
- Chimney β above nearby rooflines; check local rules. See siting distance and chimney height.
- Waste storage β a locked, covered area for waste waiting to be burned.
- Ash storage β sealed containers or an ash pit above the water table.
- Access β for the truck or forklift delivering the unit.
- PPE and tools β gloves, goggles, respirator, ash tools.


Delivery and Commissioning
- MWI-20 and MWI-30 ship assembled in a wooden crate; larger models are wrapped in protective PE film and loaded into a container, with chimney sections.
- We provide the foundation drawing, operation manual and remote guidance.
- First firing: check burners, fan, interlocks and temperature display, then run a test burn.
- Train operators before routine use β see our operator training guide.
Read more in our installation and site preparation guide.
Get the Foundation Drawing With Your Quote
Tell us your site, power supply and fuel β we’ll send the model recommendation, quotation and installation requirements.
FAQ
Does a small medical incinerator need a special building?
No. A concrete pad with a roof or simple shelter is usually enough. Check local rules for distance to buildings.
Can the MWI-20 run on household 220V power?
The MWI-20 and MWI-30 run on 220V at 50 or 60 Hz. Confirm the available current with your electrician.
How tall is the chimney?
6 m on the MWI-20 and MWI-30 and 10 m on the MWI-50. It can be extended if your authority requires.
How long does installation take?
With the foundation ready, installation and commissioning of a small unit is quick. We confirm details for your project.